EOQ Calculator
Work out the economic order quantity: how many to order each time so the cost of placing orders plus the cost of holding stock comes out as low as it can. With the EOQ formula, a worked example, and what it costs to order a little more or less.
Units sold or used. The formula needs a year, so a month counts 12 times and a week 52.14 times (365 / 7).
What it costs to keep one in stock for a year, as a share of what you pay for it. 20% to 30% is a common starting estimate.
- Orders a year
- 6
- Time between orders
- about every 61 days
- Ordering cost a year
- $300
- Holding cost a year
- $300
- Ordering plus holding, a year (not the goods)
- $600
    = √(2 × 1,200 × 50 ÷ 3)
    = √40,000
    = 200 units
The yearly cost is flat near the EOQ, so you can round to a case or a supplier's minimum and lose very little.
| Order quantity | Orders a year | Cost a year | vs the EOQ |
|---|---|---|---|
| 100 | 12 | $750 | +25% |
| 160 | 7.5 | $615 | +2.5% |
| 200EOQ | 6 | $600 | — |
| 240 | 5 | $610 | +1.7% |
| 300 | 4 | $650 | +8.3% |
The EOQ formula
The economic order quantity (EOQ) is the order size that makes the yearly cost of placing orders plus the yearly cost of holding stock as low as it can be. Order in small lots and you pay for a lot of orders. Order in big lots and you pay to store, insure and tie up cash in stock you have not used yet. EOQ is the point between the two.
EOQ = √(2 × D × S ÷ H)
- DUnits you use in a year. A month counts 12 times.
- SCost of placing one order, the same whatever the quantity.
- HCost of holding one unit in stock for a year.
The price you pay for the goods is not in the formula. It is the same per unit whatever size you order in, so it cannot change the answer. It only comes back in when the price changes with the quantity (see When EOQ does not fit, below).
Worked example: a cabinet shop's drawer slides
- Drawer slides used (D)100 pairs a month = 1,200 a year
- Cost to place one order (S)$50
- Holding cost (H)25% a year of $12 = $3 a pair
- EOQ = √(2 × 1,200 × 50 ÷ 3)√40,000 = 200 pairs
- Orders a year (1,200 ÷ 200)6, about every 61 days
- Ordering cost a year (6 × $50)$300
- Holding cost a year (200 ÷ 2 × $3)$300
- Ordering plus holding, a year$600
At the EOQ the two yearly costs come out equal, $300 each. That is where the total is lowest, and it is a quick way to check a calculation done by hand. The holding cost uses half the order (200 ÷ 2), because stock runs down from a full delivery to nothing, so on average you hold half of it.
Close to the EOQ is good enough
The total cost is flat near the bottom. In the example, ordering 240 instead of 200 costs $610 a year instead of $600 (1.7% more), and 160 costs $615 (2.5% more). Halving the order to 100 costs $750 (25% more). So round the EOQ to the case size, pallet or price break your supplier uses: landing near it matters, hitting it exactly does not.
The same flatness forgives rough inputs. If the holding cost you entered were twice the real figure, the EOQ would come out at 142 instead of 200, and ordering 142 really costs about 6% more a year than the best. Your estimates do not need to be exact. The table under the calculator shows the yearly cost at quantities around your own EOQ.
EOQ is how many. The reorder point is when.
EOQ sets the size of each order and says nothing about when to place it. That is the reorder point: the stock level that covers what you use while the order is on its way, plus a buffer. In the example, if the supplier takes 2 weeks and you keep 20 pairs of safety stock, the reorder point is 100 a month ÷ 30.4 days × 14 days + 20 = 66.03, which rounds up to 67. When stock falls to 67 pairs, order 200.
Work out the when with the reorder point calculator and the buffer with the safety stock calculator.
When EOQ does not fit
EOQ assumes you use stock at a steady rate, that the unit price is the same whatever you order, and that the order arrives in one go. Where that is not true, adjust:
- Price breaks. If the supplier charges less per unit above a quantity, the price of the goods now changes with the order size and belongs back in the sum. Work out the total yearly cost, goods included, at the EOQ and at each break quantity, and take the lowest.
- Minimum orders and pack sizes. If the supplier sells in cases of 50 or has a minimum order, round to a quantity you can actually buy. Near the EOQ that costs little.
- Lumpy or seasonal demand. For a job that needs 400 at once, or a season that doubles usage, order for the job, or work out the EOQ for each season with that season's usage.
- Short shelf life. If stock expires, spoils or goes out of date before you would use an EOQ's worth, the shelf life caps the order.
Frequently asked questions
What is the EOQ formula?
What counts as the ordering cost (S)?
What is the holding cost (H)?
Do I have to order exactly the EOQ?
How does EOQ relate to the reorder point?
When does EOQ not fit?
Is what I type sent anywhere?
Want the when kept for you?
This page works out how many to order. InventoryQuick keeps the reorder point: put it on an item as its minimum stock and the item shows as low once its total across locations is at or below it. Flat monthly plans from $19/mo, with no per-user fees.
Start 7-Day TrialReorder point calculator → · Safety stock calculator → · Inventory turnover calculator → · All free tools →